Japan
PCT - NATIONAL PHASE ENTRY
Patent Term: 20 years
Deadline: 30 months
Language: English
Translation: Japanese translation must be submitted within 2 months from entering the national phase
Charge for Excess Claims: No
Examination Request: A request for substantive examination must be filed within 3 years from the international filing date; PPH possible
Required Documents: POA - not required
Annuities: Annuities for the first 3 years are paid with the grant fee; subsequent annuities are due yearly, starting in the 3rd year
PARIS CONVENTION - DIRECT FILING
Patent Term: 20 years
Deadline: 12 months
Language: English
Translation: Japanese translation must be submitted within 14 months from the priority date
Charge for Excess Claims: No
Examination Request: A request for substantive examination must be filed within 3 years from the filing date; PPH possible
Required Documents: POA - not required; Certified copy of priority application required within 16 months (no translation needed for priority doc)
Annuities: Annuities for the first 3 years are paid with the grant fee; subsequent annuities are due yearly, starting in the 3rd year
DESIGN APPLICATION
Patent Term: 20 years
Deadline: 6 months from priority
Language: English
Translation: Not required
Charge for Excess Claims: No
Examination Request: No specific request for substantive examination needs to be filed with JPO; undergoes formal and substantive examination
Required Documents: POA - not required; Certified copy of priority doc within 3 months from filing date; front page translation into Japanese
Annuities: Renewal fees are payable every year after the grant
TRADEMARK APPLICATION
Patent Term: 10 years
Deadline: N/A
Language: English
Translation: Front page of priority document must be translated into Japanese
Charge for Excess Claims: No
Examination Request: Not explicitly required
Required Documents: POA - not required; Certified copy of priority doc must be submitted within 3 months of filing; front page translation into Japanese
Annuities: Trademark is renewable every 10 years